Contract Agreement Amount

Rs. 43,96,679

Physical Progress

55.00%

Financial Progress

49.90%

Remaining Payment

Rs. 50

Roadway Excavation and Strucutral Works on Solukhumbu Coppermine (Tamakhani) Approach Road, Waksa, Solukhumbu

Office: डिभिजन सडक कार्यालय, हर्कपुर, ओखलढुङगा (175)

Fiscal Year: 077-78

55.00%

Contract Date: 21-Feb-21

Start Date: 21-Feb-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.