Contract Agreement Amount

Rs. 2,69,76,581

Physical Progress

62.00%

Financial Progress

49.88%

Remaining Payment

Rs. 50

Construction of RCC motorable Bridge over Sarkindhara Khola along Gumi Patihalna Sadak, Surkhet

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 073-74

62.00%

Contract Date: 7-Sep-17

Start Date: 8-Sep-17

Completion Date: 07-Sep-2018 (EOT Not Done)