Contract Agreement Amount

Rs. 52,43,826

Physical Progress

97.51%

Financial Progress

49.87%

Remaining Payment

Rs. 50

Road Improvement Works Including Drain and Cross Drainage along Chudamani Chowk Jhagar Tole Dhanpati Tole Bakullachap Madhuban Jane Sadak Kalopattre, Sunsari

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

97.51%

Contract Date: 21-Mar-22

Start Date: 21-Mar-22

Completion Date: 13-Jan-2023 (EOT Done)