Contract Agreement Amount

Rs. 1,26,11,008

Physical Progress

0.00%

Financial Progress

49.75%

Remaining Payment

Rs. 50

Road maintenance works including earthworks,drainage and structural works from Deurali to Phasinda Dovan (28+000 to 50+000)

Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)

Fiscal Year: 076-77

0.00%

Contract Date: 24-Nov-19

Start Date: 24-Nov-19

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.