Contract Agreement Amount
Rs. 48,57,117
Physical Progress
98.66%
Financial Progress
49.66%
Remaining Payment
Rs. 50
Blacktopped Road Construction Works including Drainage Structures along Lohendraghat-Judipul - satarbasti hudai Thlha Baudha Sadak Morang.
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 076-77
Contract Date: 19-Nov-19
Start Date: 19-Nov-19
Completion Date: 12-May-2020 (EOT Done)
Project Description
No description available.