Contract Agreement Amount
Rs. 7,07,45,641
Physical Progress
50.00%
Financial Progress
49.60%
Remaining Payment
Rs. 50
Road Pavement Works along Dharke-Sitapaila Road, NH21, Dhading
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 079-80
Contract Date: 12-Oct-22
Start Date: 12-Oct-22
Completion Date: 30-Jun-2023 (EOT Not Done)
Project Description
No description available.