Contract Agreement Amount
Rs. 1,23,44,698
Physical Progress
0.00%
Financial Progress
49.49%
Remaining Payment
Rs. 50
ad including Drainage Structure along Chaudhary Tole Madhesa School Ba Si Sadak, Sunsari
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 076-77
Contract Date: 12-Jul-20
Start Date: 12-Jul-20
Completion Date: 12-Apr-2021 (EOT Done)
Project Description
No description available.