Contract Agreement Amount
Rs. 26,41,458
Physical Progress
66.14%
Financial Progress
49.44%
Remaining Payment
Rs. 50
Recurrent Maintenance work along Duhabi Inaruwa Sadak, sunsari
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 077-78
Contract Date: 30-Oct-20
Start Date: 30-Oct-20
Completion Date: 11-Apr-2022 (EOT Done)
Project Description
No description available.