Contract Agreement Amount
Rs. 14,66,885
Physical Progress
97.45%
Financial Progress
49.36%
Remaining Payment
Rs. 50
Recurrent Maintenace work along MRM Ithari to Inarwa Section (CH.092+000 to 109+000)
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 077-78
Contract Date: 12-Nov-20
Start Date: 12-Nov-20
Completion Date: 13-May-2021 (EOT Done)
Project Description
No description available.