Contract Agreement Amount
Rs. 3,76,03,283
Physical Progress
0.00%
Financial Progress
49.18%
Remaining Payment
Rs. 50
Supplying and Fixing of Highway Street Light
Office: ब्यापारिक मार्ग बिस्तार आयोजन, बेलहिया बुटवल सडक , रुपन्देही (133)
Fiscal Year: 076-77
Contract Date: 5-Mar-20
Start Date: 12-Mar-20
Completion Date: 06-Mar-2021 (EOT Done)
Project Description
No description available.