Contract Agreement Amount

Rs. 1,64,40,547

Physical Progress

0.00%

Financial Progress

49.18%

Remaining Payment

Rs. 50

Construction of Causeway,Rcc drain, gabion, stone masonary,Box culvert Works along Godar(Dhanusa) chisapani-mainabati -kalapani-dudhauli-sindhuli NH79 (from Shiv Mandir to Crusher Rakheko Samm)

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 077-78

0.00%

Contract Date: 9-Apr-21

Start Date: 9-Apr-21

Completion Date: 13-Apr-2022 (EOT Not Done)

Project Description

No description available.