Contract Agreement Amount
Rs. 1,39,86,011
Physical Progress
76.30%
Financial Progress
49.00%
Remaining Payment
Rs. 51
Pavement Work including Cross Drainage and Retaning Structures Along Sombare Madangram- Satpidi hudai Bhauda Sadak,Ratuwamai, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 077-78
Contract Date: 20-Dec-20
Start Date: 20-Dec-20
Completion Date: 14-Jul-2021 (EOT Done)
Project Description
No description available.