Contract Agreement Amount

Rs. 3,60,72,798

Physical Progress

100.00%

Financial Progress

48.93%

Remaining Payment

Rs. 51

Construction of RCC Bridge over Baniyani Khola near Mate School Dharampur-4 and 5, Basnet Tole, Jhapa.

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 073-74

100.00%

Contract Date: 19-Jun-17

Start Date: 19-Jun-17

Completion Date: 16-Feb-2019 (EOT Done)

Project Description

No description available.