Contract Agreement Amount

Rs. 4,59,65,836

Physical Progress

49.00%

Financial Progress

48.80%

Remaining Payment

Rs. 51

Construction of Blacktopped Works on Birtamode Sainikmode Sainik Bajar Goldhap Road, Jhapa

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 078-79

49.00%

Contract Date: 2-Mar-22

Start Date: 2-Mar-22

Completion Date: 08-Jul-2022 (EOT Not Done)

Project Description

No description available.