Contract Agreement Amount
Rs. 5,40,43,570
Physical Progress
0.00%
Financial Progress
48.61%
Remaining Payment
Rs. 51
Construction of Rupse Khola Bridge (PSC Girder 1 X 35m) Along Beni Jomsom Road, Myagdi
Office: कालिगण्डकी कोरिडोर (बेनी जोमसोम कोरोला सडक योजना), जोमसोम, मुस्ताङ (223)
Fiscal Year: 074-75
Contract Date: 23-Sep-18
Start Date: 23-Sep-18
Completion Date: 07-Oct-2020 (EOT Not Done)
Project Description
No description available.