Contract Agreement Amount
Rs. 99,63,776
Physical Progress
29.00%
Financial Progress
48.44%
Remaining Payment
Rs. 51
Roadway Excavation,Construction of Gabion/Masonry Wall,Side Drain,HumePipe Cuvert and Gravelling Works in Deurali(Thanti)(chainage 146+000) to Khanadaha(Chainage 156+000) section of Ridi-Balkot-Hanspur-Pyuthan-Surkhet Road
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 077-78
Contract Date: 23-Feb-21
Start Date: 23-Feb-21
Completion Date: 16-Nov-2021 (EOT Done)
Project Description
No description available.