Contract Agreement Amount

Rs. 99,63,776

Physical Progress

29.00%

Financial Progress

48.44%

Remaining Payment

Rs. 51

Roadway Excavation,Construction of Gabion/Masonry Wall,Side Drain,HumePipe Cuvert and Gravelling Works in Deurali(Thanti)(chainage 146+000) to Khanadaha(Chainage 156+000) section of Ridi-Balkot-Hanspur-Pyuthan-Surkhet Road

Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)

Fiscal Year: 077-78

29.00%

Contract Date: 23-Feb-21

Start Date: 23-Feb-21

Completion Date: 16-Nov-2021 (EOT Done)

Project Description

No description available.