Contract Agreement Amount

Rs. 36,15,07,409

Physical Progress

75.83%

Financial Progress

48.38%

Remaining Payment

Rs. 51

Design & Build of Seven Bridges along Madan Bhandari Highway (Botechaur-Bhedabari-Dhuliyabit Section), Surkhet

Office: पुर्वाञ्चल क्षेत्रिय सडक निर्देशनालय, झापा (7)

Fiscal Year: 078-79

75.83%

Contract Date: 27-Feb-22

Start Date: 27-Feb-22

Completion Date: 19-Aug-2024 (EOT Not Done)

Project Description

No description available.