Contract Agreement Amount

Rs. 2,59,02,554

Physical Progress

0.00%

Financial Progress

48.34%

Remaining Payment

Rs. 51

Construction of Asphalt Concerte & Box Culvert Along tarapatti Pathara MRM puspalpur NH30 Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 076-77

0.00%

Contract Date: 6-Feb-20

Start Date: 6-Feb-20

Completion Date: 08-Oct-2021 (EOT Done)

Project Description

No description available.