Contract Agreement Amount

Rs. 6,30,01,052

Physical Progress

47.63%

Financial Progress

48.27%

Remaining Payment

Rs. 51

Maintenance works and Special Protection works in Landslide zones of Belkhet - Binayak, Binayak - Thatikadh, Thatikadh - Mangalsen, Kailash khola - Bayalpata Road sections of Midhill Highway, Achham.

Office: Unknown (503)

Fiscal Year: 078-79

47.63%

Contract Date: 19-May-22

Start Date: 19-May-22

Completion Date: 16-Oct-2024 (EOT Done)

Project Description

No description available.