Contract Agreement Amount
Rs. 75,57,728
Physical Progress
77.00%
Financial Progress
48.21%
Remaining Payment
Rs. 51
Roadway Excavation/Blactop Pavement/ Masonry Wall/ Plum Drain/ RCC Pavement etc. construction along Kaligandaki Pul- Baglung Khanda NH03
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 078-79
Contract Date: 3-Mar-22
Start Date: 3-Mar-22
Completion Date: 14-Jan-2023 (EOT Done)
Project Description
No description available.