Contract Agreement Amount
Rs. 5,40,16,190
Physical Progress
96.00%
Financial Progress
48.05%
Remaining Payment
Rs. 51
Bridge Protection approach road and river training works on Trishuli River bridge Thimura-Devghat Road
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 076-77
Contract Date: 12-Jun-20
Start Date: 15-Jun-20
Completion Date: 15-Jun-2020 (EOT Not Done)
Project Description
No description available.