Contract Agreement Amount
Rs. 1,50,34,892
Physical Progress
0.00%
Financial Progress
48.04%
Remaining Payment
Rs. 51
Construction of RCC Bridge (Multicell Box-Culvert) above Sarnchiya Nadi
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 076-77
Contract Date: 9-Feb-20
Start Date: 9-Feb-20
Completion Date: 05-Jan-2021 (EOT Done)
Project Description
No description available.