Contract Agreement Amount
Rs. 13,78,57,667
Physical Progress
52.00%
Financial Progress
47.78%
Remaining Payment
Rs. 52
Widenning of NepalgunjRapti Bridge section along Nepalgunj Baghauda Road ,Banke
Office: Unknown (1)
Fiscal Year: 079-80
Contract Date: 23-Oct-22
Start Date: 23-Oct-22
Completion Date: 31-Oct-2024 (EOT Not Done)
Project Description
No description available.