Contract Agreement Amount

Rs. 37,76,77,216

Physical Progress

47.36%

Financial Progress

47.36%

Remaining Payment

Rs. 52

Upgrading of road to Black top-291~292+340,293+320-298,302~304+521-CAB/Gwallek JV

Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)

Fiscal Year: 078-79

47.36%

Contract Date: 4-Jul-22

Start Date: 4-Jul-22

Completion Date: 04-Jul-2025 (EOT Not Done)

Project Description

No description available.