Contract Agreement Amount
Rs. 15,22,57,248
Physical Progress
48.00%
Financial Progress
47.25%
Remaining Payment
Rs. 52
Design &Build of Dudhaura River Bridge,Along East West Highway,Bara,(BBPCU-DB-3373204-074/75-001
Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)
Fiscal Year: 074-75
Contract Date: 8-Jul-18
Start Date: 8-Jul-18
Completion Date: 07-Jul-2021 (EOT Not Done)
Project Description
No description available.