Contract Agreement Amount
Rs. 26,62,05,000
Physical Progress
50.00%
Financial Progress
47.19%
Remaining Payment
Rs. 52
Design and Build of Bridge over Jhapri Khola, Seti Rajmarga (Kailali-Doti-Achham), Kailali
Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)
Fiscal Year: 078-79
Contract Date: 9-Feb-23
Start Date: 9-Feb-23
Completion Date: 14-May-2026 (EOT Not Done)
Project Description
No description available.