Contract Agreement Amount
Rs. 5,44,29,874
Physical Progress
60.00%
Financial Progress
47.01%
Remaining Payment
Rs. 52
Construction of Tamadi Khola Bridge along Pokhara Baglung Road, Sadh Khola Pul-Maldhunga Road Section Parbat
Office: Unknown (406)
Fiscal Year: 078-79
Contract Date: 13-Oct-22
Start Date: 13-Oct-22
Completion Date: 10-Feb-2024 (EOT Not Done)
Project Description
No description available.