Contract Agreement Amount
Rs. 1,24,96,484
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction of Tengra Khola Bridge, Itahari-2 to Pashupati Chowk-4 Redcross
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 067-68
Contract Date: 14-Jul-11
Start Date: 14-Jul-11
Completion Date: 09-Jul-2017 (EOT Done)
Project Description
No description available.