Contract Agreement Amount
Rs. 2,45,27,795
Physical Progress
0.00%
Financial Progress
46.82%
Remaining Payment
Rs. 53
Construction of Pre-Stressed RCC Bridge (Pile Foundation) in Soti Khola Bridge
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 072-73
Contract Date: 15-Sep-16
Start Date: 23-Sep-16
Completion Date: 05-Jun-2019 (EOT Done)
Project Description
No description available.