Contract Agreement Amount
Rs. 1,11,56,716
Physical Progress
0.00%
Financial Progress
46.77%
Remaining Payment
Rs. 53
Road Improvement Works (Rigid Pavement) on Hatisar Fettepur Inarwa Bhalui Road, Bara
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 075-76
Contract Date: 7-Jun-19
Start Date: 7-Jun-19
Completion Date: 14-Jul-2019 (EOT Not Done)
Project Description
No description available.