Contract Agreement Amount

Rs. 67,85,860

Physical Progress

60.00%

Financial Progress

46.77%

Remaining Payment

Rs. 53

Roadway Excavation, Structural Cross Drainage and Gravelling Works on Bhimad-Rampur-Mityal-Arunkhola(Dhunganabesi-Mityal section) Road

Office: सडक डिभिजन, पाल्पा (27)

Fiscal Year: 078-79

60.00%

Contract Date: 14-Feb-22

Start Date: 28-Feb-22

Completion Date: 09-Jul-2022 (EOT Not Done)