Contract Agreement Amount
Rs. 3,28,30,450
Physical Progress
46.64%
Financial Progress
46.64%
Remaining Payment
Rs. 53
Construction of feme khola bridge
Office: डिभिजन सडक कार्यालय, ईलाम (12)
Fiscal Year: 074-75
Contract Date: 13-Mar-18
Start Date: 15-Mar-18
Completion Date: 06-Sep-2019 (EOT Not Done)