Contract Agreement Amount
Rs. 13,59,41,992
Physical Progress
46.30%
Financial Progress
46.33%
Remaining Payment
Rs. 53
Construction of Tamar River Bridge of Tamar River.
Office: डिभिजन सडक कार्यालय, धनकुटा (15)
Fiscal Year: 068-69
Contract Date: 10-Jul-12
Start Date: 15-Jul-12
Completion Date: 30-Jun-2023 (EOT Done)