Contract Agreement Amount
Rs. 47,72,524
Physical Progress
94.00%
Financial Progress
46.19%
Remaining Payment
Rs. 53
Upgrading works of kiratichaap dudhpokhari 21 kilo Road
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 076-77
Contract Date: 25-Dec-19
Start Date: 25-Dec-19
Completion Date: 09-Oct-2020 (EOT Done)
Project Description
No description available.