Contract Agreement Amount

Rs. 20,80,206

Physical Progress

50.00%

Financial Progress

44.71%

Remaining Payment

Rs. 55

Improvement of Mariyaghat-Thapapur-Jhabai-Bauniya Road, Kailali (Ch 9+500 To 9+695 from Border), Kailali

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 077-78

50.00%

Contract Date: 26-Nov-20

Start Date: 3-Dec-20

Completion Date: 08-May-2021 (EOT Not Done)