Contract Agreement Amount

Rs. 88,89,265

Physical Progress

100.00%

Financial Progress

44.26%

Remaining Payment

Rs. 55

Rigid Pavement and drain works

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 077-78

100.00%

Contract Date: 29-Nov-20

Start Date: 29-Nov-20

Completion Date: 12-Apr-2021 (EOT Not Done)

Project Description

No description available.