Contract Agreement Amount

Rs. 5,53,80,262

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Construction of Seto khola Bridge, Lete (concrete girder 1*25m) along Beni Jomsom road,Mustang

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 079-80

0.00%

Contract Date: 26-Jun-23

Start Date: 26-Jun-23

Completion Date: 26-Jun-2023 (EOT Not Done)

Project Description

No description available.