Contract Agreement Amount
Rs. 43,95,204
Physical Progress
0.00%
Financial Progress
43.86%
Remaining Payment
Rs. 56
खलंगा मार्के कालीमाटी रामपुर कोहलपुर सडक
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 073-74
Contract Date: 14-May-17
Start Date: 14-May-17
Completion Date: 26-Dec-2017 (EOT Done)
Project Description
No description available.