Contract Agreement Amount
Rs. 7,00,57,964
Physical Progress
44.00%
Financial Progress
43.86%
Remaining Payment
Rs. 56
Roadway Excavation and Structure works along Jorayal Sahajpur Road, Doti
Office: सुनसरी मोरङ्ग पुल निर्माण आयोजना, सुनसरी (66)
Fiscal Year: 078-79
Contract Date: 1-Aug-22
Start Date: 1-Aug-22
Completion Date: 01-Dec-2023 (EOT Not Done)
Project Description
No description available.