Contract Agreement Amount
Rs. 1,68,84,874
Physical Progress
50.00%
Financial Progress
43.47%
Remaining Payment
Rs. 56
RoadWay Excavation,Structural Works,Drainage Works Bartung-Tansen-Ridi Section
Office: पुर्वाञ्चल क्षेत्रिय सडक निर्देशनालय, झापा (7)
Fiscal Year: 079-80
Contract Date: 16-Nov-22
Start Date: 16-Nov-22
Completion Date: 30-Jun-2023 (EOT Not Done)