Contract Agreement Amount

Rs. 1,68,84,874

Physical Progress

50.00%

Financial Progress

43.47%

Remaining Payment

Rs. 56

RoadWay Excavation,Structural Works,Drainage Works Bartung-Tansen-Ridi Section

Office: पुर्वाञ्चल क्षेत्रिय सडक निर्देशनालय, झापा (7)

Fiscal Year: 079-80

50.00%

Contract Date: 16-Nov-22

Start Date: 16-Nov-22

Completion Date: 30-Jun-2023 (EOT Not Done)

Project Description

No description available.