Contract Agreement Amount
Rs. 54,73,895
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction of Sallaghari- Duwakot Road, Bhaktapur.
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 074-75
Contract Date: 30-Oct-17
Start Date: 30-Oct-17
Completion Date: 30-Dec-2018 (EOT Done)
Project Description
No description available.