Contract Agreement Amount
Rs. 85,79,061
Physical Progress
0.00%
Financial Progress
43.43%
Remaining Payment
Rs. 56
Consrtuction of HPC and Blacktop Works at Tarapatti- Uttimpur Laliya Sadak, Dhanusha
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 075-76
Contract Date: 25-Mar-19
Start Date: 25-Mar-19
Completion Date: 28-May-2020 (EOT Done)