Contract Agreement Amount

Rs. 85,79,061

Physical Progress

0.00%

Financial Progress

43.43%

Remaining Payment

Rs. 56

Consrtuction of HPC and Blacktop Works at Tarapatti- Uttimpur Laliya Sadak, Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 075-76

0.00%

Contract Date: 25-Mar-19

Start Date: 25-Mar-19

Completion Date: 28-May-2020 (EOT Done)

Project Description

No description available.