Contract Agreement Amount

Rs. 1,26,22,72,461

Physical Progress

33.11%

Financial Progress

43.34%

Remaining Payment

Rs. 56

Upgrading to Blacktop ( Asphalt Concrete works) of Tamor Corridor ( Mulghat Majhitar Amarpurdanda Subhang Ganeshchwok Road Section NH-06 109+000 to 155+260

Office: सडक विभाग, काठमाण्डौ (2)

Fiscal Year: 079-80

33.11%

Contract Date: 5-Dec-22

Start Date: 5-Dec-22

Completion Date: 31-May-2025 (EOT Not Done)

Project Description

No description available.