Contract Agreement Amount

Rs. 12,50,14,881

Physical Progress

60.00%

Financial Progress

42.94%

Remaining Payment

Rs. 57

Construction ofRCC Prestressed Motorable Bridge over Bhangaha river in Dhanusha district(Bhuckkkar-Pashupatinagar road between Bateshwar Ga. Pa. and Bhangaha Na. Pa.)

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 075-76

60.00%

Contract Date: 8-Feb-19

Start Date: 8-Feb-19

Completion Date: 08-Aug-2021 (EOT Not Done)

Project Description

No description available.