Contract Agreement Amount
Rs. 52,73,135
Physical Progress
44.00%
Financial Progress
42.90%
Remaining Payment
Rs. 57
Roadway Excavation and structural works on Belkhet-Talagad-Bhanakot Road Section, Achham
Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)
Fiscal Year: 079-80
Contract Date: 7-Dec-22
Start Date: 13-Dec-22
Completion Date: 13-Apr-2023 (EOT Not Done)
Project Description
No description available.