Contract Agreement Amount
Rs. 6,24,94,570
Physical Progress
42.87%
Financial Progress
41.79%
Remaining Payment
Rs. 58
Blacktop and roadway improvement works
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 072-73
Contract Date: 8-Aug-16
Start Date: 8-Aug-16
Completion Date: 29-Mar-2023 (EOT Done)
Project Description
No description available.