Contract Agreement Amount

Rs. 7,74,61,528

Physical Progress

45.00%

Financial Progress

41.66%

Remaining Payment

Rs. 58

Construction of Modi Khola Bridge, Jhuka-Serabesi-Nayapul-Pokhara Sadakko Jhuka Deuraali, Parbat ra Salyan V.D.C. ka bich maa parne pul (2*30 m)

Office: Road Division, Baglung (254)

Fiscal Year: 074-75

45.00%

Contract Date: 16-Dec-18

Start Date: 16-Dec-18

Completion Date: 16-Oct-2020 (EOT Not Done)

Project Description

No description available.