Contract Agreement Amount

Rs. 1,04,64,536

Physical Progress

45.00%

Financial Progress

41.24%

Remaining Payment

Rs. 58

Rehabilitation Works on Harkapur - Okhaldhunga - Salleri Road (Siddhicharan Rajmarg) at Ch. 46+000 to 100+000 Section, Okhaldhunga & Solukhumbu

Office: डिभिजन सडक कार्यालय, हर्कपुर, ओखलढुङगा (175)

Fiscal Year: 077-78

45.00%

Contract Date: 27-Apr-21

Start Date: 27-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.