Contract Agreement Amount

Rs. 4,79,04,613

Physical Progress

0.00%

Financial Progress

41.14%

Remaining Payment

Rs. 58

मुतनी नदी पुल, फकहा बरदहीको विचमा, सप्तरी, सिराहा

Office: डिभिजन सडक कार्यालय, सिराहा (16)

Fiscal Year: 072-73

0.00%

Contract Date: 23-May-16

Start Date: 23-May-16

Completion Date: 23-May-2018 (EOT Not Done)

Project Description

No description available.