Contract Agreement Amount
Rs. 74,51,298
Physical Progress
0.00%
Financial Progress
41.08%
Remaining Payment
Rs. 58
Recurrent Maintenance Works along Hetauda- Chure- Pathalaiya Section of TRP
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 077-78
Contract Date: 4-Apr-21
Start Date: 4-Apr-21
Completion Date: 07-Jul-2021 (EOT Not Done)
Project Description
No description available.